Construction Details...

The Lean-to Design

Orientation:  North-facing
Size:  Floor-space ~ 4.4 x 4.4 m
Drying surface:  15 sq.m
Roofing:  15° slope, Novalite fibreglass (clear) or corrugated iron

Site Requirements for hillside location:

Lean-to elevation

Pre-construction requirements:

Allow plenty of space surrounding the drier for ...

The Starting Point:

Construction must start with the central concrete wall. This wall fixes the position, floor height and orientation of the completed unit.  It must be straight and level and at least 0.5 – 0.6m. into the earth below its lower-side ground-level.
If the ground is not too steep (less than 10°) the two outer retaining walls could well be omitted.