Materials

Below is a cutting list of timber for the basic Lean-to design using a roof-sheet length of 3m.

Structure Part Size([mm]
Lgth [m.]
Qty. (HS)*
Qty. (LV)
Retaining walls concrete 0.9 x 0.1m
9 - 10
3
-
Side walls (block\poured) concrete 0.5 x 0.1m
5 - 6
4
-
Foundations (building) Posts 100 x 150
0.9 - 1.4
16
20
  Wall cap 100 x 50
5
1
-
  Bearers 150 x 50
5
4
5
  Joists 100 x 50
2.6
16
-
  " 100 x 50
5.2
-
8
Rails Posts 100 x 150
1.2
16
20
  Rails (vassa) 100 x 50
4.5
12
12
  Rail doublers 100 x 50
4.5
6
4
  Guide strips 50 x 50
4.5
16
12
Building Flooring 100 x 25
4.5
36
36
  Baffle boards 150 x 25
4.5
16
12
  Wall framing 75 x 50
4.5
8
8
  " 75 x 50
2.5
4
16
  " 75 x 50
1.5
24
12
  (nogs, extras) 75 x 50
(16m)
1
1
Roof Rafters 100 x 50
5.8
8
-
  " 100 x 50
3.2
-
16
  Purlins 75 x 50
5.8
7
15
  Facia (gutter) 150 x 25
5.8
1
2
  Facia (gables) 150 x 25
6.4
2
2
  Barge (optional) 150 x 25
6.4
2
2
Walling Exterior (vertical) 150 x 25
3.6
16
16

HS = lean-to design;  LV = centrally vented design

The list above shows only the amounts used and approximate sizes of timber within the structure.  It does not include concrete boxing, pegs and other general building requirements, e.g. offcuts. 
In practice a further 15-20% more will be needed.

Drying trays:   See elsewhere for material ideas.
Cement:   The retaining walls as described will require 32-36 bags (40kg).